Industrial LEV testing checklist

Free industrial LEV testing checklist for the COSHH thorough examination and test: preparation, system checks, hood readings, report and follow-up.

Updated Sources checked

How often: Usually at least every 14 months; Schedule 4 sets 1-month or 6-month limits for specified processes. Follow any shorter interval for your system.

Sections
7
Checks
51
Critical
0
Sources
53

0/36 answered

0%

Answers, comments and photos stay on this device. Nothing is sent to Irada.

Details such as lev system name or number and where the system is are kept with each inspection you run in Irada. The printout has lines for them.

1

Type of system *

When an item fails

A hood that fails its test is marked, reported and repaired. HSE guidance for examiners is to label every hood tested and give a red label, or equivalent, to any that fail [10]. Employers fill in the logbook and get the repairs done [18].

  • Treat the thorough examination report as an audit and improve the system where it falls short [16].
  • Until the hood is repaired, look at how workers are exposed at that point and add interim controls if they need them.
  • Keep records of examinations, tests and repairs for at least five years [2].

Run it with your team in Irada

  • Schedule it per site and assign it to the right people.
  • Turn every failed check into a corrective action that someone else verifies.
  • Keep signatures, photos and the full audit history across sites.
Use this checklist Print with your logo

Answers on this page stay on this device; they are not transferred.

Frequently asked questions

How often does LEV need to be tested?

Usually at least every 14 months [21]; the specified Schedule 4 processes have 1-month or 6-month limits [1]. The interval can also be shorter: the commissioning report should say if the testing frequency differs from the statutory 14 months [5].

How long do I need to keep LEV test records?

Keep the thorough examination and test record for at least 5 years [21]. Information on the installed system that shows it gives adequate protection, such as the commissioning report, should be kept for the life of the equipment [35].

Do LEV hoods have to have airflow indicators?

There is no specific legal requirement to fit airflow indicators [23], but you should have some way of checking that adequate airflow is being maintained [24]. HSE notes that an airflow indicator is currently the only method that shows the operator or supervisor immediately if there is a problem [34].

Does LEV have to be labelled after testing?

There is no specific legal requirement on employers or examiners to label LEV [38]. HSE guidance recommends that examiners label each hood with a test record [37], and put a red "Failed" label on any hood or system that has failed [47]. After repair, a competent person checks that it is effective before the label comes off [28].

What should I do if part of the LEV fails the test?

The report should clearly show what is wrong and what needs to be done to correct it [48]. Act on the recommendations in the report [22], and review your COSHH assessment where examination and test results suggest it is no longer valid [3].

Does on-tool extraction need a thorough examination and test?

Yes. The extraction unit should be thoroughly examined and tested at least every 14 months [45]. If you hire the unit, you are responsible for making sure it is not used after its test has expired while it is on hire to you [31].

Built from 53 official sources

Every check traces to the text it is based on. Read the purpose, how to use it, the rules behind it, what it does not cover and every source.

Guidance, not legal advice. It does not replace the law, the manufacturer's instructions or your organization's competent people, and completing it does not certify that work is safe.